Raiden Resources enters option to earn up to 80% of Zambia Copper Domes Project from Lobito Resources

Raiden Resources (ASX: RDN)11 November 2026

Headline consideration

US$350,000

Scheduled cash if option exercised, or US$365,000 if the extension is used

Interest acquired

Up to 80%

Staged earn-in through shares in Lobito or an agreed Zambian special purpose vehicle

Summary

Raiden Resources Limited (ASX: RDN) has entered into a Binding Option and Earn-In Agreement with Lobito Resources Limited for the Zambia Copper Domes Project. Under the agreement, Raiden may earn up to an 80% interest in the project, which comprises a single exploration licence of approximately 507 km² in North-Western Province, Zambia. The company states that, if the option is exercised, scheduled cash consideration totals US$350,000, or US$365,000 if the discretionary extension is used, excluding management fees, exploration, studies, other project costs and applicable taxes and duties. Raiden has an exclusive three-month option from execution to undertake due diligence and elect to proceed with the earn-in. The company states that Schedule 1 of the announcement is not exhaustive and that the agreement contains other terms it considers customary for transactions of this nature.

Consideration

ComponentTerms
Initial option feeUS$50,000, together with the first monthly option fee of US$15,000, payable within seven days of execution
Monthly option feesFurther US$15,000 monthly option fees payable during the option period
Option extensionThe discretionary one-month extension requires an additional US$15,000 extension fee, as well as the monthly option fee for that month
Payment on exerciseUS$150,000 less the monthly option fees already paid
Deferred considerationUS$150,000 twelve months after exercise. The initial option fee and extension fee are not credited against these payments
Scheduled cash considerationIf the option is exercised, totals US$350,000, or US$365,000 if the discretionary extension is used, excluding management fees, exploration, studies, other project costs and applicable taxes and duties
Stage 1 – 51% interestFund and complete 6,500 metres of reverse circulation and/or diamond drilling within 24 months of option exercise, subject to extension and drilling carry-forward provisions
Stage 2 – 65% interestFurther 14% interest by funding and completing a further 7,000 metres of drilling, for 13,500 metres in total, within 24 months of the Stage 1 acquisition notice. Raiden may elect to proceed within 120 days of that notice
Stage 3 – 75% interestFurther 10% interest by funding and announcing a positive Pre-Feasibility Study on ASX within 24 months of the Stage 2 acquisition notice. Raiden may extend this period by 12 months by written notice
Stage 4 – 80% interestFurther 5% interest by announcing a decision to mine on ASX. No fixed deadline is specified for this stage
Management feeFrom option exercise, Raiden and Lobito will enter into a country management agreement, in place up to the point where Raiden earns a 51% interest
Royalty on dilutionAn interest diluted below 10% converts to a 1.5% net smelter return royalty. The non-diluting shareholder may purchase 0.5 percentage points of that royalty for US$2.5 million, reducing it to 1%
Facilitation feePayable to an unrelated party: A$50,000 on exercise of the election and a further A$50,000 on the 12-month anniversary of the exercise, each in cash or RDN shares at the Company’s election

Conditions

  • Completion of due diligence by Raiden during the exclusive three-month option period, which may be extended by one additional month
  • Zambian Minerals Regulation Commission approval for Raiden’s acquisition of control and any required licence consent, which Lobito must seek. These are not conditions to exercising the option, but exploration under the earn-in cannot commence until the option has been exercised and the approvals obtained
  • Required land-access consents and environmental approvals for the relevant fieldwork and drilling
  • Satisfaction of the Stage 1 reporting requirements before Raiden may elect to proceed to Stage 2

Source: Raiden Resources announcement dated 11 November 2026. This page summarises information from the company's public announcement and is provided for general information only. It is not financial product advice, a recommendation or an offer, and it does not take into account any person's objectives, financial situation or needs. Figures and terms are taken from the announcement and may be incomplete or may have changed since publication. Refer to the original announcement for full details. Kamoa Capital has not independently verified the information.